Friday, April 12, 2019

TetraTech - Waughop Lake Dredging Feasibility Water Quality Analysis - June 20 2018

 Executive Summary

The management goal for Waughop Lake is to reduce the intensity and duration of Cyanobacteria blooms resulting in harmful algal blooms (HAB) events, while improving the overall water quality and aquatic habitat that supports a recreational fishery. To attain this goal there are 6 potential alternatives that could be implemented; 4 include dredging alternatives to remove phosphorus-rich sediment and 2 are alum treatment alternatives that are directly targeting phosphorus to prevent HABs through phosphorus inactivation (making phosphorus unavailable to aquatic plants). Due to the uncertainty of the sediment depth needed to be removed to meet the management goals, there is a shallow dredging and deep dredging alternative, each with and without direct phosphorus inactivation via alum treatments.

The dredging alternatives 50-year life-cycle cost range from $7,900,000 to $34,500,000 with a probability of success (increasing water quality while reduced HABs) ranging from 20% to 90% over the 50-year period. The 50-year life-cycle cost for the two alum treatment alternatives range from $2,500,000 to $3,300,000 with a probability of success ranging from 75% to 85% over the 50-year period.

The dredging alternatives would result in no direct use of the lake for almost 1 year during dredging activities and no use of 60 to 100 acres of park land for 1 year, plus limited lake access for 1 week per year from year 2 through 50. The alum treatment alternatives would result in limited lake access for 1 week each year for the 50-year period.

General Discussion

Based upon the available information presented in the Waughop Lake Management Plan by Brown and Caldwell the following is a brief outline of a dredging approach for Waughop Lake. Due to data gaps and necessary assumptions, this discussion includes alternative dredging actions with additional alternative management actions relative to effectiveness in controlling HAB events and water quality improvements. The assumed management goal is to reduce the intensity and duration of HAB events, while improving the overall water quality and aquatic habitat within Waughop Lake. Previous studies and reporting have assumed that dredging will give the lake a 50-year period of good water quality without additional significant efforts needed. This assumption does not truly account for the role of groundwater phosphorus inputs and internal sediment phosphorus loading from sediment not removed in the proposed dredging process. It also does not consider the necessity to inactivate sediment phosphorus (remove the potential for phosphorus to become biologically available) from the newly exposed lake water/sediment interface, (Gibbons, et al 1983).

The purpose of lake sediment removal (i.e. dredging) is to remove the reservoir of phosphorus that is assumed to be currently contributing to excessive production of cyanobacteria. The effectiveness of dredging in Waughop Lake is dependent upon two undefined phosphorus loading potentials; 1) depth of sediment phosphorus contributing to the cyanobacteria production and 2) the impact of groundwater relative to its direct contribution of phosphorus to the lake and groundwater inflow through the lake sediments contributing to sediment phosphorus availability to the water column. This translates into two dredging alternatives depending upon depth of sediment to be removed. It also requires the inactivation of remaining sediment phosphorus that will be exposed after dredging and the inactivation of phosphorus brought into the lake via groundwater.

A viable dredging approach is to employ a hydraulic dredge to minimize water contamination and to remove phosphorus most efficiently. This approach would assume that sediment would be dredged and removed from the lake at a 5% solids content. This dredgate would be pumped from the hydraulic dredge to a treatment pond near the lake.

Assuming a pond depth of 9.8 ft (3 m), the area of the pond would be 18 to 20 acres (7.3 to 8.1 ha) (Figure 1). The treatment pond would need to be constructed above grade and lined to prevent interaction with groundwater. As the dredgate enters the pond, a flocculate (either a polymer or alum) would need to be added to aid in dewatering the dredgate and retaining phosphorus in the dredge spoils. The pond would be designed to have four cells. Three cells would store one day’s worth of the treated dredgate (approximately 26,150 yd3 (20,000 m3) at 1,307 yd3 (1000 m3) of lake sediment) to allow the dewatering to occur over 24 to 72 hours.

Clarified water would then be transferred via inverted syphon to the remaining pond cell for additional clarification. Water would then be removed from the fourth pond cell and returned to the lake after passing through a sediment curtain. This would translate to approximately 20,915 yd3 (16,000 m3) per day of water returning to the lake.

Dewatered dredgate would be transferred to a composting disposal site assuming that metal and other contaminate concentrations in the sediment do not require hazard waste disposal. Note that sediment metal concentrations reported would not allow disposal of dredgate to crop lands. Therefore, disposal would be to a landfill, or non-crop landscape, i.e. park and golf course sites. Landfill disposal cost would be very high due to limited land fill capacity and this could drive dredging cost higher than potentially stated in this memo.

For cost savings, it was assumed that the park would be the site for the dewatering pond and dredgate disposal. Hence, the dredgate would be transferred to a soil spreader to place 6” of dredgate over 66 acres or 12” over 33 acres as shown in Figure 1. This would be done at a rate of 1” per 7 seven days.

Dredging will result in a direct impact to park use in the areas of the treatment pond and disposal site for the period of operation. Park use and access would also be severely limited post dredging to allow the plant community to recover. See Figure 1 for proposed dredgate disposal areas and treatment pond location. It would be at least a year before park use within these areas could be allowed. The estimated total area of park to be impacted, excluding the lake, is approximately 60 to 100 acres. If off site dredgate disposal is utilized the impacted park area would be approximately 30 to 40 acres.

Small Dredge Volume Alternative

Due to the lack of current depth profile sediment data, it was assumed that approximately 3.3 ft (1 m) of sediment will need to be removed over 30 acres (12.1 ha). It was also assumed that groundwater inflow will replace any water removed from the lake via the hydraulic dredging process. Specifically, at 1,307 yd3 (1,000 m3) of sediment removed per day, with a total dredgate of 26,150 yd3 (20,000 m3), 24,850 yd3 (19,000 m3) of lake water would be removed per day. Total volume of sediment removed would be 158,700 yd3 (121,400 m3). Dredging would take approximately 30 days for mobilization including temporary treatment pond construction and dredge pipeline installation, 120 days for dredging, and another 30 days for final dredgate disposal and pond deconstruction with both sites replanted.

Following the dredging operation within the lake, a phosphorus sediment inactivation, combined with a water stripping treatment using alum, would be necessary to bind newly exposed sediment phosphorus, with the added benefit of clearing the water column. Again, due to the lack of sediment profile of phosphorus fractions the dose of that treatment was assumed to be 4 mg Al/L for water column phosphorus removal and 40 mg Al/L for sediment inactivation, for a one-time total dose of 44 mg Al/L. This sediment inactivation treatment would take place within 5 days of the sediment removal completion within the lake.

To address on-going loading of phosphorus to the lake via groundwater, an annual spring alum treatment at a dose of 4 mg Al/L would be needed to remove and inactive phosphorus for external sources (mainly groundwater) to prevent extreme HAB events. This annual dose would be further refined with lake and groundwater monitoring data.

Small Dredge Volume Alternative without Phosphorus Inactivation or Annual Control
This alternative is the same as the dredging option described above to remove 158,700 yd3 (121,400 m3) of sediment, but without the alum addition to inactivate newly exposed sediment phosphorus and annual phosphorus loading to the lake via, i.e. groundwater.

Large Dredge Volume Alternative

Due to the lack of current depth profile sediment data, it was assumed that approximately 6.6 ft (2 m) of sediment will need to be removed over 30 acres (12.1 ha). It was also assumed that groundwater inflow will replace any water removed from the lake via the hydraulic dredging process. Specifically, at 1,307 yd3 (1,000 m3) of sediment removed per day, with a total dredgate of 26,150 yd3 (20,000 m3), 24,850 yd3 (19,000 m3) of lake water would be removed per day. Total volume of sediment removed would be 317,400 yd3 (242,800 m3). Dredging would take approximately 30 days for mobilization including temporary treatment pond construction and dredge pipeline installation, 240 days for dredging, and another 30 days for final dredgate disposal and pond deconstruction with both sites replanted.

Following the dredging operation, a phosphorus sediment inactivation treatment would be necessary to bind newly exposed sediment phosphorus. As stated above, the dose of that treatment is assumed to be 4 mg Al/L for the water column phosphorus removal and 40 mg Al/L for the sediment inactivation for a total dose of 44 mg Al/L. This sediment inactivation treatment would take place within 5 days of the sediment removal completion within the lake.

To address the on-going loading of phosphorus to the lake via groundwater an annual spring alum treatment at a dose of 4 mg Al/L would be needed to remove and inactive phosphorus from external sources to prevent extreme HAB events. This annual dose would be further refined with lake and groundwater monitoring data.

Large Dredge Volume Alternative without Phosphorus Inactivation or Annual Control
This alternative is the same as the large dredging option described above to remove 315,400 yd3 (242,800 m3) of sediment, but without the alum addition to inactivate newly exposed sediment phosphorus and annual phosphorus loading to the lake via groundwater.

Phosphorus Inactivation and/or Annual Phosphorus Control without Dredging

The dose for an alum treatment without dredging is assumed to be 4 mg Al/L for water column phosphorus removal and 80 mg Al/L for sediment inactivation, based on the limited sediment phosphorus data available. If sediment cores were collected and analyzed for detailed phosphorus fractions and these data showed less phosphorus potential, the estimated dose of 80 mg Al/L could be reduced. Based on the currently available data, the total dose would be 84 mg Al/L. Due to cost and a relatively high dose, the alum treatment could be conducted over a 2 to 4-year period with an annual maintenance alum treatment to address on-going loading of phosphorus to the lake, mainly via groundwater inputs. An annual spring alum treatment at a dose of 4 mg Al/L would be needed to remove and inactive phosphorus from external sources on an annual basis following the sediment phosphorus inactivation dosing.

See Table 1 for relative costs and effectiveness assessment of the alternatives. Costs are based upon recent lake dredging operations and alum treatments conducted within the state. Effectiveness assessments are based upon both literature and direct experience with lake dredging projects since 1979 and alum lake treatments since 1974 throughout the US to improve water quality and control phosphorus

Insights and Recommendations

It is highly recommended, to both save costs and ensure the potential of achieving the lake management goal of reducing the number and intensity of HAB events in Waughop Lake, that three sediment cores of at least 6.6 ft (2m) depth be collected and analyzed every 5 cm for phosphorus fractions. This would cost about $15,000 but could result in 25 to 50% alum treatment costs savings.

To assess the effectiveness and plan for dredging and/or alum treatment, the sediment composition of Waughop Lake must be characterized. Specifically, the amount of phosphorus that is available to be released from the lake sediments (and must be removed by dredging and/or inactivated by alum) must be quantified. Therefore, all forms of phosphorus in every 5-cm sediment layer for at least 2-meter depth of sediment must be characterized including, total phosphorus (TP), mobile phosphorus (Mobile- P), organic phosphorus, biogenic phosphorus, Aluminum bound phosphorus (Al-P), and calcium bound P (Ca-P). Total phosphorus is a sum of all the components together. Mobile-P is the phosphorus that is susceptible to changes in the oxidative conditions and is the sum of iron-bound phosphorus (Fe-P) and loosely-bound phosphorus. Mobile-P can also consist of a portion of organic and biogenic phosphorus that is released through mineralization.

Based upon the probability of attaining the management goal for Waughop Lake, the relative impact to park users and the relative estimated life-cycle costs of dredging and alum treatments, it is recommended that a phased management approach be implemented at the lake. This approach would first include an alum treatment to inactivate the sediment phosphorus over a 2 to 4-year period and then implement annual alum maintenance treatments. This management strategy would result in improved water quality and reduced HABs, while also significantly reducing the life-cycle costs. It would also limit the impacted park area to just the lake for approximately 1 week per year, compared to at least 1 year of limited access of both the park (60 to 100 acres) and the lake for the dredging alternatives.

No comments:

Post a Comment